Saturday, 20 February 2021/Published inStorage Tanks
MATEN SECOMOC’s Tank 102 Double Wall Tank Project at GAPCO Terminal II, Mombasa for Total Kenya PLC nearing its completion. Great job by our team while working with ever-changing weather conditions to be safe and on schedule!
Wednesday, 16 December 2020/Published inStorage Tanks
The tank Bottom and first shell done, first jack-up completed as well. Assembly of the fixed dome roof in progress at MATEN SECOMOC’s Tank 102 Project at GAPCO Terminal II, Mombasa for Total Kenya PLC. The scope of work entails the conversion of Tank 102 from a single shell to a double-shell tank.
Successful swapping of tanks by re-routing the pipelines, conversion of non-piggable line to piggable and installation of pressure control valves, strainers and pressure gauges on 14 tanks including all the associated pipework at Total Kenya’s Ltd facility in Mombasa.